The City of Cape Town’s Water and Sanitation Directorate has advised that various parts of the Mother City will experience water supply disruptions this week as the team conducts planned work on its water supply infrastructure, reports Cape {town} Etc.
The following areas will be affected:
Maintenance work: pipe and valve installations, repairs and replacements
Mfuleni, Driftsands and Khayelitsha
- Monday, 17 March, from 10am to 1pm
- Thursday, 20 March, from 8am to 8pm
The water supply to these areas will be shut off temporarily to enable the directorate’s maintenance team to assess the valves leading off the 1065mm diameter water supply.
The temporary shut-off will also allow the directorate to assess which areas will be impacted by the actual shut-off set to take place on Thursday.
According to the City, the impacted areas could not be reduced due to a limited number of control valves on this bulk water supply network. Therefore, water tankers will be made available to provide water for domestic use where required.
Bishop Lavis, Klipkop, Parow Valley, Parow Industria and Ravensmead
- Tuesday, 18 March, from 11am to 2pm
- Thursday, 20 March, from 8am until 8am on Saturday, 22 March
The water supply to these areas will be shut off temporarily to enable the maintenance team to assess the areas that will be impacted by the actual shut-off set to take place from Thursday to Saturday.
According to the City, the shut-off will allow the maintenance team to safely install two 535mm diameter water meters in the newly installed chamber at the Tygerberg Reservoir.
Residents are advised that alternate water supply will be rerouted to the affected areas during this time albeit at lower-than-usual pressures. Some residents may also briefly experience slight discolouration in their water supply due to the changeover of supply.
What residents need to know about larger-scale planned water supply disruptions
The City says careful consideration has been given to the planning of this work to ensure it is being done at a time that is least disruptive to the water supply.
However, maintenance work can sometimes be more complex than anticipated, resulting in longer-than-expected periods of water supply disruptions.
Additionally, all sites where water and sanitation repairs and upgrades are conducted are deemed to be construction sites and, as such, are off-limits to members of the public.
The City advises that for a short period after the water supply is restored, the water may be discoloured or milky in appearance due to the presence of trapped air in the pipes. If left to stand, the water will become clear in colour again.
How to prepare
Residents are encouraged to keep taps closed to prevent any water loss and/or damage, as well as store enough water in clean, sealed containers to last during this period.
Also read: