The Western Cape Government has provided a detailed explanation for why a lane on the N1 inbound near Sable Road has been closed and is causing significant traffic congestion.
Also read: Watch: BMW driver narrowly escapes falling tree in Cape Town storm
The province’s Department of Infrastructure closed certain lanes on the N1 inbound near Sable Road due to large pools of water on the road following two weeks of heavy rain.
The Western Cape Government’s engineering teams are on-site looking for alternative ways to supplement the stormwater drainage process.
In addition to routine maintenance, teams will clear the earth drains and perform specialised high-pressure cleaning of the pipe culverts.
The province said: ‘Our engineering teams have liaised with the City of Cape Town and other organs of state to attempt to tap into other existing systems to allow for the N1 stormwater drainage system to recover before the next major storm event.’
‘Unfortunately, the Western Cape government cannot predict how quickly the excess water will take to drain away so that all three lanes of the roadway can be reopened.’
The area is gradually drying out, and the road will reopen once it is safe to do so.
Cape {town} Etc discount: Looking for things to do in the city, at half the price? Get exclusive offers here.
The province acknowledged that these lane closures were causing significant congestion.
The wetland’s earth berm, adjacent to the N1, has been breached resulting in excess water flowing from the wetland onto the N1 road reserve.
‘As a result of the wetland’s inability to hold and absorb the water, the roadway has flooded. This is due to the compounded impact of several days of rain over the current wet season.’
‘Over time, the soil will become less waterlogged, water will be absorbed into the ground, the flooding will abate, and it will be possible to reopen all three lanes of the N1 in this location.’
‘The stormwater drainage system is designed to ensure that water moves from one side of the N1 to the other via a number of pipe culverts or along open drainage systems to where it ultimately discharges near the Koeberg Interchange, some 2km away from the current flooded area,’ the province said.
The stormwater drainage system on this section of the N1 was designed to handle only road-related water runoff.
Any stormwater drainage system is designed to deal with a specific set of circumstances, but two weeks of heavy rain have exceeded the system’s capacity, leaving it unable to handle the additional pressure and water from the wetland area.
The Western Cape Government’s response consists of three phases.
The short-term/initial phase focused on ensuring road user safety through advance warnings, delineators and other measures.
Yesterday, multiple parties attempted to pump water from the area, but as predicted by the City’s specialist team of engineers, this did not produce results.
Pumping continued throughout the night and early hours of yesterday morning, including pumping to other sections of the drainage system, which is why the Sable Road off-ramp was closed.
Water was pumped through the existing system to help it recover along its natural flow path to the Koeberg interchange.
Find your perfect set of wheels with these incredible deals on cars for under 100k. Find car listings here.
Pumping the water into tankers and transporting it offsite was also considered, but conservative estimates showed that the submersible pumps would only produce an approximate capacity of 120m3/hour, taking more than three days to remove the water with a round-the-clock operation.
The use of sandbags to increase the capacity of side drains was also tested, but the results were insufficient, and no new lanes could be opened.
‘Road users will note large equipment and plant over the past two days which are trying to create additional capacity in the system. This will continue along with regular high-pressure cleaning of drainage pipes and culverts to ensure no debris brought about by the flooding clogs the system.’
The department has also allocated additional resources from another contractor to assist with the efforts of the maintenance teams over the last week or so.
‘We hope that this additional commitment will yield more favourable results. Currently the teams are working with Prasa, the City of Cape Town and the South African National Defence Force (Ysterplaat Air Force Base) to find additional points where water could be relayed to,’ the province said.
The long-term response would include creating additional capacity in the wetland but also increasing the capacity of the stormwater system along the N1.
Advocate Chantal Smith, head of the Department of Infrastructure, said: ‘I can confirm that our team of engineers and teams on the ground are using all appropriate measures and techniques to address the problem as soon as possible.
‘We wish to thank road users for their patience, we understand your frustrations. Thank you also to our teams who are working tirelessly and through the night to find solutions and to our partners for their support.’
Infrastructure MEC Tertuis Simmers said: ‘I want to assure the public that our department is fully committed to resolving this issue as swiftly and efficiently as possible. The safety of our road users is our top priority, and we are deploying all available resources to manage the situation.’
‘We understand the inconvenience this causes and appreciate your patience and cooperation as we work through these challenges. Together, with our dedicated teams and partners, we will restore normalcy to this critical route.’